The Thiruvananthapuram City Roads Improvement Project (TCRIP) in Kerala involved constructing, operating, and maintaining 10 corridors and 3 NH-bypass links totaling ~102.08 km under a Build-Operate-Maintain-and-Transfer (Annuity) Model. The project was developed in four phases and the first phase has been handed back to the Authority. The project has been operational for last 11 Years.
| Project: | Thiruvananthapuram City Road Improvement Project (Phase- I, II, III & IV) of 42.403 Km of city roads in the State of Kerala |
|---|---|
| Type of Roads: | City Roads |
| Length: | 102.08 km |
| State: | Kerala |
| Authority: | Kerala Road Fund Board |
| Phase | Length | Length | Concession End Date |
|---|---|---|---|
| Phase I | 14.268 km (51 lane-km) | 4th July 2007 | July 4, 2022 |
| Phase II | 15.739 km (61 lane-km) | 22nd Feb 2012 | February 22, 2027 |
| Phase III | 7.600 km (25 lane-km) | 20th Feb 2015 | February 20, 2030 |
| Phase IV | 4.455 km (21 lane-km) | 31st May 2016 | May 31, 2031 |